Vizsla Silver Corp. (AMEX:VZLA) has postponed its anticipated first silver production at the Panuco silver-gold project in Sinaloa, Mexico, to the second half of 2028, a year later than its previous target of the second half of 2027.
The revised timetable reflects ongoing permitting requirements, site readiness considerations and construction scheduling, as the company prepares for a phased return to operations at the project.
Despite the delay, Vizsla Silver reported continued progress on engineering, equipment procurement and development contracts, while maintaining the financial and operating assumptions outlined in its November 2025 Feasibility Study.
The company also confirmed that it has not yet made a formal production decision for Panuco.
Vizsla Silver reported that engineering work at Panuco is approximately 50% complete, with M3 Engineering & Technology overseeing the engineering programme.
The company has also placed orders for approximately 85% of the equipment required for the project’s processing plant.
Three development contracts have been awarded, covering engineering, procurement and construction management, mine design, and equipment supply.
However, the principal mining contract remains outstanding and has yet to be finalised.
The progress on engineering and equipment procurement indicates that development preparations are continuing, although the revised production schedule reflects the additional time required to complete permitting, site preparation and construction activities.
The company has not provided a new detailed construction timetable beyond its revised target for first production in the second half of 2028.
Security considerations remain an important component of Vizsla Silver’s preparations to resume activity at the Panuco project site.
The company said it continues to work with Mexican federal authorities and independent security advisers to develop the infrastructure and arrangements required for a phased return.
Vizsla Silver referred to the “tragic events of January 2026” in its announcement but did not provide additional details about those events.
The company indicated that safety considerations are guiding its approach to restarting site activities.
President and Chief Executive Officer Michael Konnert confirmed that “first silver production is now expected in the second half of 2028”, while emphasising that the safety of personnel remains central to preparations for a phased return.
The revised timetable reflects the company’s intention to address site readiness and security requirements before advancing further development activities.
Vizsla Silver confirmed that it is not revising the operating, capital expenditure or economic assumptions contained in its November 2025 Feasibility Study.
The study outlined average annual production of approximately 17.4 million ounces of silver equivalent.
It also estimated an after-tax net present value of $1.8 billion using a 5% discount rate, alongside an internal rate of return of 111%.
The projected investment payback period was approximately seven months.
These estimates were calculated using assumed commodity prices of $35.50 per ounce for silver and $3,100 per ounce for gold.
Initial capital expenditure was estimated at $238.7 million.
The company has retained these assumptions despite the revised production schedule, although the figures have not been updated to reflect the later start date.
The economic projections therefore remain those presented in the November 2025 study rather than revised estimates incorporating the additional development time.
Alongside the project update, Vizsla Silver announced a $5 million commitment to establish the Vizsla Foundation.
The initiative is intended to support communities surrounding the Panuco project through programmes focused on education, healthcare and economic development.
The company also plans to allocate a percentage of future profits to the foundation, providing a potential source of ongoing funding once the project becomes operational and generates earnings.
The initiative reflects Vizsla Silver’s stated intention to support local communities alongside the development of its mining operations.
Further details regarding the foundation’s programmes, funding arrangements and implementation timetable were not provided in the announcement.
Although Vizsla Silver has advanced engineering and procurement activities, the company confirmed that it has not yet taken a formal decision to proceed with production at Panuco.
The revised first-production target of the second half of 2028 therefore remains a development objective rather than a confirmed operational start date.
Progress towards that target will depend on permitting, security arrangements, site readiness, completion of outstanding contracts and the subsequent construction schedule.
The company’s decision to retain the November 2025 Feasibility Study assumptions also means that the potential financial implications of the revised development timetable have not been incorporated into updated project economics.
Investors will be monitoring further announcements for information on the phased return to site, construction progress and the timing of a formal production decision.
Vizsla Silver’s latest announcement confirms a one-year delay to the anticipated start of silver production at Panuco, while highlighting continued progress on engineering and equipment procurement.
With approximately half of the engineering work completed and 85% of processing plant equipment ordered, the company has advanced several elements of its development programme.
However, permitting, security preparations and construction scheduling remain important factors affecting the project’s timetable.
The November 2025 Feasibility Study continues to provide the basis for the company’s published economic expectations, including average annual production of 17.4 million ounces of silver equivalent and an estimated after-tax net present value of $1.8 billion.
The revised production target, together with the absence of a formal production decision, leaves the timing and eventual financial performance of the project dependent on further development milestones.
Vizsla Silver stock price
| Nov-19 | |
| Nov-19 | |
| Oct-09 | |
| Sep-17 | |
| Sep-15 | |
| Sep-08 | |
| Sep-02 | |
| Aug-26 | |
| Aug-05 | |
| Jul-14 | |
| Jun-17 | |
| Jun-16 | |
| May-26 | |
| May-21 | |
| May-19 |
Join thousands of traders who make more informed decisions with our premium features. Real-time quotes, advanced visualizations, alerts, and much more.
Learn more about Finviz Elite