- Joined the Russell 2000® and 3000® Indexes as of June 30, 2025
- SEALMINER A3 series almost ready for mass production
- Increased self-mining hashrate by 21% to 16.5 EH/s on continued deployment of SEALMINERs
SINGAPORE, July 09, 2025 (GLOBE NEWSWIRE) -- Bitdeer Technologies Group (NASDAQ: BTDR) (“Bitdeer” or the “Company”), a world-leading technology company for Bitcoin mining, today announced its unaudited mining and operations updates for June 2025.
Operational Update
Management Commentary
“In June, we increased our self-mining hashrate by 21% to 16.5 EH/s and we remain on track to reach 40 EH/s by the end of October 2025,” said Matt Kong, Chief Business Officer at Bitdeer. “For SEALMINER A3, the machine level testing is ongoing with all the test results meeting expectations and mass production is almost ready. Looking forward, we are also excited about our most ambitious chip yet, the SEAL04, and we’re building real momentum toward our long-term vision of being a leading global ASIC manufacturer.”
Mr. Kong continued, “In addition, we are honored to be included in the U.S. Russell Indexes, a significant milestone that reflects Bitdeer’s continued growth and execution as a leading technology company. We look forward to the increased visibility among institutional investors and improved trading liquidity that the Russell Indexes brings as we advance our advanced SEALMINER technology roadmap, rapidly scale our global Bitcoin mining operations and further diversify into HPC/AI.”
Production and Operations Summary
Metrics | June 2025 | May 2025 | June 2024 |
Total hash rate under management1 (EH/s) | 30.6 | 27.4 | 22.3 |
- Proprietary hash rate | 16.7 | 13.7 | 8.5 |
• Self-mining | 16.5 | 13.6 | 7.3 |
• Cloud Hash Rate | - | - | 1.2 |
• Delivered but not hashing | 0.2 | 0.1 | - |
- Hosting | 13.9 | 13.7 | 13.8 |
Mining rigs under management | 200,000 | 189,000 | 223,000 |
- Self-owned2 | 114,000 | 103,000 | 86,000 |
- Hosted | 86,000 | 86,000 | 137,000 |
Bitcoins mined (self-mining only) | 203 | 196 | 179 |
Bitcoin held3 | 1,502 | 1,351 | 113 |
1 Total hash rate under management as of June 30, 2025 across the Company’s primary business lines: Self-mining, Cloud Hash Rate, and Hosting.
2 Self-owned mining machines are for the Company’s self-mining business and Cloud Hash Rate business.
3 Bitcoins held do not include the Bitcoins from deposits of the customers.
Infrastructure Construction Update
Site / Location | Capacity (MW) | Status | Timing4 |
Electrical capacity | |||
- Rockdale, Texas | 563 | Online | Completed |
- Knoxville, Tennessee | 86 | Online | Completed |
- Wenatchee, Washington | 13 | Online | Completed |
- Molde, Norway | 84 | Online | Completed |
- Tydal, Norway | 120 | Online | Completed |
- Gedu, Bhutan | 100 | Online | Completed |
- Jigmeling, Bhutan | 132 | Online | Completed |
Total electrical capacity | 1,0985 | ||
Pipeline capacity | |||
- Tydal, Norway Phase 2 | 105 | In progress | Q3 2025 |
- Massillon, Ohio | 221 | In progress | Q3 - Q4 2025 |
- Clarington, Ohio Phase 1 | 266 | In progress | Q2 2027 |
- Clarington, Ohio Phase 2 | 304 | In planning | Q2 2027 |
- Jigmeling, Bhutan | 368 | In progress | Q3 2025 |
- Rockdale, Texas | 179 | In planning | Estimate 2026 |
- Alberta, Canada | 99 | In planning | Q4 2026 |
- Oromia Region, Ethiopia | 50 | In progress | Q4 2025 |
Total pipeline capacity | 1,592 | ||
Total global electrical capacity | 2,690 |
4 Indicative timing. All timing references are to calendar quarters and years.
5 Figures represent total available electrical capacity.
Rockdale, Texas – 100 MW Hydro-cooling conversion energization is ongoing:
Tydal, Norway – 175 MW site expansion has commenced energization and the full energization timeline has been adjusted to the end of Q3 2025:
Massillon, Ohio – 221 MW site on track for completion in H2 2025:
Clarington, Ohio – 570 MW total, in 2 phases:
Jigmeling, Bhutan – 500 MW site has commenced energization and is expected to be fully energized in phases by the end of Q3 2025:
Fox Creek, Alberta – 101 MW site acquired in Alberta, is fully licensed and permitted to construct an on-site natural gas power plant. The project is expected to be energized by the end of Q4 2026.
Oromia Region, Ethiopia – SPA and a turnkey agreement signed for the acquisition and construction of a 50 MW Bitcoin mining project in Ethiopia. The project is expected to be energized in Q4 2025.
Upcoming Conferences and Events
About Bitdeer Technologies Group
Bitdeer is a world-leading technology company for Bitcoin mining. Bitdeer is committed to providing comprehensive Bitcoin mining solutions for its customers. The Company handles complex processes involved in computing such as equipment procurement, transport logistics, datacenter design and construction, equipment management, and daily operations. The Company also offers advanced cloud capabilities to customers with high demand for artificial intelligence. Headquartered in Singapore, Bitdeer has deployed datacenters in the United States, Norway, and Bhutan. To learn more, visit https://ir.bitdeer.com/ or follow Bitdeer on X @ BitdeerOfficial and LinkedIn @ Bitdeer Group.
Investors and others should note that Bitdeer may announce material information using its website and/or on its accounts on social media platforms, including X, formerly known as Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages investors and others to review the information it posts on the social media and other communication channels listed on its website.
Forward-Looking Statements
Statements in this press release about future expectations, plans, and prospects, as well as any other statements regarding matters that are not historical facts, may constitute “forward-looking statements” within the meaning of The Private Securities Litigation Reform Act of 1995. The words “anticipate,” “look forward to,” “believe,” “continue,” “could,” “estimate,” “expect,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “should,” “target,” “will,” “would” and similar expressions are intended to identify forward-looking statements, although not all forward-looking statements contain these identifying words. Actual results may differ materially from those indicated by such forward-looking statements as a result of various important factors, including factors discussed in the section entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as well as discussions of potential risks, uncertainties, and other important factors in Bitdeer’s subsequent filings with the U.S. Securities and Exchange Commission. Any forward-looking statements contained in this press release speak only as of the date hereof. Bitdeer specifically disclaims any obligation to update any forward-looking statement, whether due to new information, future events, or otherwise. Readers should not rely upon the information on this page as current or accurate after its publication date.
For investor and media inquiries, please contact:
Investor Relations
Orange Group
Yujia Zhai
[email protected]
Public Relations
BlocksBridge Consulting
Nishant Sharma
[email protected]
Jul-09 | |
Jul-03 | |
Jun-30 | |
Jun-30 | |
Jun-28 | |
Jun-25 | |
Jun-24 | |
Jun-20 | |
Jun-20 | |
Jun-19 | |
Jun-18 | |
Jun-17 | |
Jun-17 | |
Jun-11 | |
May-20 |
Join thousands of traders who make more informed decisions with our premium features. Real-time quotes, advanced visualizations, backtesting, and much more.
Learn more about FINVIZ*Elite