(All amounts in US$ unless otherwise indicated)
Thacker Pass Phase 1 mechanical completion remains on track for late 2027, with ramp-up to commercial production expected in 2028. Updated capital cost estimate provided, with anticipated capital needs expected to be funded through available sources.
VANCOUVER, British Columbia--(BUSINESS WIRE)--$LAC #Nevada--Lithium Americas Corp. (TSX: LAC) (NYSE: LAC) (“Lithium Americas,” “LAC” or the “Company”) announced an update on its Thacker Pass lithium project in Humboldt County, Nevada (“Thacker Pass” or the “Project”). Mechanical completion of Thacker Pass Phase 1 construction is targeted for late 2027, with ramp-up through 2028. Once at full production capacity, Thacker Pass is expected to produce nominal 40,000 tonnes per year of battery-quality lithium carbonate.1




Jonathan Evans, President and Chief Executive Officer of Lithium Americas, said, "Thacker Pass is on track to deliver America's largest fully integrated source of domestic battery-quality lithium carbonate, and we are building it at pace. Phase 1 is advancing toward peak construction activity by year end 2026, with mechanical completion targeted for late 2027. Despite external and internal factors impacting the Project’s capital cost estimate, the anticipated capital cost for Thacker Pass are expected to remain funded as we continue to deliver on our execution plan and bring the Project safely into production. As construction advances to piping and electrical installation, we are building our Operations and Business Readiness team to support the transition from developer to operator."
Mr. Evans added, "Lithium is a strategic asset, and Thacker Pass is the nation's clearest near-term path to a reliable domestic supply. As one of the largest construction projects in Nevada, the Project is already putting nearly 2,000 skilled craftspeople to work in Humboldt County, and that number is still growing. This Project will help anchor the supply chains driving American economic competitiveness and support growing demand from the lithium-ion battery markets for electric vehicles and energy stationary storage. Thacker Pass is essential to America's economic and national security, and we are committed to delivering it."
CONSTRUCTION UPDATE
Mechanical completion of Thacker Pass Phase 1 construction is targeted for late 2027, with ramp-up through 2028. As of September 30, 2026 (unless otherwise indicated):
| __________________ | ||
1 | See the Company's NI 43-101 technical report dated effective December 31, 2024, "National Instrument 43-101 Technical Report - Thacker Pass Project, Humboldt County, Nevada, USA" for full details. | |
UPCOMING CONSTRUCTION MILESTONES
The following Project development milestones are targeted for the remainder of 2026:
DEFINITIVE CAPEX ESTIMATE UPDATE
The Company has completed an updated Capex Estimate for Thacker Pass Phase 1 that reflects achieving advanced levels of construction, detailed engineering and procurement and further incorporates external factors, which have arisen following declaration of the final investment decision (“FID”) in April 2025. The updated Capex Estimate of $3.83 billion (including contingency) represents an increase from the prior Capex Estimate of $2.93 billion and reflects:
The Capex Estimate risk profile has been lowered with advanced levels of engineering and procurement completed, all earthworks and geotechnical risks have passed, and all remaining key long-lead equipment is expected to mobilize to site during November 2026. Further, the number of craft workers already on site lowers the risk associated with being able to achieve peak labor requirements by the end of 2026. For the remainder of construction, primary risks include costs associated with attraction and retention of quality craft labor and sustaining planned installation rates.
The incremental funding requirement associated with the updated Capex Estimate is anticipated to be met mainly through Company contributions and available U.S. Department of Energy (“DOE”) loan (“DOE Loan”) reserve funding. See the Project Financing section below for more details.
2026 CAPEX GUIDANCE
The Company’s previously disclosed capital expenditure guidance (“Capex Guidance”) for fiscal year 2026 has been updated to reflect changes to the total overall Project capital expenditure, as outlined above. As a result, the Company is targeting a capital expenditure range of $1.7 billion to $2.0 billion for Thacker Pass Phase 1 for fiscal year 2026. Peak capital expenditure is expected to be in fiscal year 2026, with the balance of capital expenditure spent throughout 2027 and into 2028 during ramp-up.
The table below summarizes certain capital costs in the nine months ended September 30, 2026 and cumulative to September 30, 2026, as well as changes to the Company’s 2026 Capex Guidance. The financial information presented in this news release is preliminary, is subject to completion of the Company’s quarter-end closing and review procedures, which are currently ongoing, and may be adjusted in the Company’s full results for the quarter ended September 30, 2026 (“Q3 2026”). It is provided solely to give context for the Project financing and liquidity update, is not a complete presentation of the Company’s Q3 2026 results and should not be viewed as a substitute for the Company’s complete Q3 2026 financial statements and management’s discussion and analysis. Other information regarding the Company’s Q3 2026 financial position and results of operations is not yet final and will be disclosed with the Company’s full Q3 2026 results. The inclusion or omission of any particular financial information in this news release should not be read as indicative of any other actual or anticipated trends in the Company’s Q3 2026 financial position or results of operations, except as expressly set forth herein. The Company will release full results for Q3 2026 on November 12, 2026.
(US$) | For the Nine Months Ended Sept 30, 2026 | Cumulative to Sept 30, 2026 | Original 2026 Capex Guidance | Change | Current 2026 Capex Guidance |
Thacker Pass Phase 1 construction costs included in the Capex Estimate(1)(2) | $1,398.7 million | $2,261.3 million | $1.2 - $1.5 billion | $0.4 billion | $1.6 - $1.9 billion |
Other capitalized development costs for Thacker Pass(3) | $21.1 million | $114.2 million | $30 - $40 million | - | $30 - $40 million |
Capitalized interest, including the Orion Notes(4) and DOE Loan | $45.1 million | $72.1 million | $45 - $55 million | $10 million | $55 - $65 million |
Total | $1,464.9 million | $2,447.6 million | $1.3 - $1.6 billion | $0.4 billion | $1.7 - $2.0 billion |
| 1 | Thacker Pass Phase 1 construction costs cumulative to September 30, 2026 and those estimated for fiscal year 2026, do not include $19.5 million and $8.0 million, respectively, of community contributions that are required to be expensed under U.S. GAAP, though these were included in the Capex Estimate. | |
| 2 | Thacker Pass Phase 1 construction costs cumulative to September 30, 2026, and those estimated for fiscal year 2026, includes actual tariffs incurred through September 30, 2026. Thacker Pass Phase 1 construction costs estimate for fiscal year 2026 also includes estimated tariff exposure, primarily for equipment and construction materials sourced from Canada, China, India, UAE, Turkey and the European Union. The Company continues to closely monitor potential tariff exposure; however, changes in tariffs and trade restrictions can be announced with little or no advance notice. Thacker Pass Phase 1 construction costs estimate for fiscal year 2026 also include an estimate for the movement in the balance of prepaid construction costs and deposits on long-lead equipment during 2026, both of which are excluded from cumulative construction costs until the goods and services have been received at Thacker Pass. | |
| 3 | Other capitalized development costs are required to be capitalized under U.S. GAAP, though these were not included in the Capex Estimate. | |
| 4 | Fund entities managed by Orion Resource Partners LP (collectively “Orion”) purchased $195.0 million in aggregate principal amount of senior unsecured convertible notes (the “Orion Notes”). |
PROJECT FINANCING
The Company estimates the incremental funding requirement arising from the Capex Estimate and other assumption changes to be approximately $995 million, summarized as follows:
Pursuant to (a) an omnibus waiver, consent and amendment (the “OWCA”) to the DOE Loan signed on November 10, 2026 (“OWCA 3”) and related loan documents, and (b) agreements among the DOE, the Company and General Motors Holdings LLC (“GM”), it is anticipated this incremental funding requirement will be fully met through, collectively, $650 million in contributions from the Company to the Thacker Pass joint venture (“JV”) level and, as and when required, $315 million currently credited to certain reserve accounts established and funded under the DOE Loan. In addition, amendments to the DOE Loan documents pursuant to the OWCA 3 will decrease the funding requirement of the Sustaining Capex Reserve Account by approximately $30 million during and after the ramp-up period of the Project. These contributions will result in an increase to the Company’s ownership percentage in the JV.
LIQUIDITY POSITION AND CAPITAL RESOURCES
The selected financial information below is preliminary and unaudited, is subject to completion of the Company’s quarter-end closing and review procedures, which are currently ongoing, and is provided solely to give context for the Project financing and liquidity update. It is not a complete presentation of the Company’s Q3 2026 results and may be adjusted in the Company’s final Q3 2026 results. Other information regarding the Company’s Q3 2026 financial position and results of operations is not yet final and will be disclosed with the Company’s full Q3 2026 results on November 12, 2026. The inclusion or omission of any particular information herein should not be read as indicative of any other actual or anticipated trends in the Company’s Q3 2026 financial position or results of operations, except as expressly set forth herein.
NEXT STEPS
The Company is working with the DOE and GM to finalize the related implications on JV interest holdings.
Mr. Evans added, “I am proud of the construction progress we have achieved to date and the focus and hard work in completing the definitive capital cost estimate while also maintaining our target of mechanical completion in late 2027. Our Board and everyone across Lithium Americas, including Bechtel, are focused on bringing Thacker Pass to full commercial production in 2028.”
ABOUT LITHIUM AMERICAS
Lithium Americas is building Thacker Pass, located in Humboldt County, in northern Nevada. Phase 1 is designed for nominal production capacity of 40,000 tonnes per year of battery-quality lithium carbonate, and mechanical completion is targeted for late 2027. Thacker Pass hosts the largest known measured lithium resource (Measured and Indicated) in the world and is owned by a JV between Lithium Americas and GM. The DOE holds a warrant to purchase common shares equivalent to a 5% equity stake of the Company as of January 30, 2026, as well as a warrant at the JV level to purchase a non-voting, non-transferable equity interest in the JV (together, the “Warrants”). Lithium Americas’ shares are listed on the Toronto Stock Exchange and New York Stock Exchange under the symbol LAC. To learn more, visit www.lithiumamericas.com or follow @LithiumAmericas on social media.
TECHNICAL INFORMATION
The scientific and technical information in this news release has been reviewed and approved by Rene LeBlanc, PhD, SME, Vice President, Commercial and Product Strategy of the Company, and a “qualified person” as defined under National Instrument 43-101 and Subpart 1300 of Regulation S-K under the United States Securities Act of 1933, as amended.
FORWARD-LOOKING STATEMENTS
This news release contains “forward-looking information” within the meaning of applicable Canadian securities legislation and “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 (collectively referred to herein as “forward-looking statements” (“FLS”)). All statements, other than statements of historical fact, are FLS and can be identified by the use of statements that include, but are not limited to, words, such as “anticipate,” “plan,” “continue,” “estimate,” “expect,” “may,” “will,” “project,” “predict,” “proposes,” “potential,” “target,” “implement,” “schedule,” “forecast,” “intend,” “would,” “could,” “might,” “should,” “believe” and similar terminology, or statements that certain actions, events or results “may,” “could,” “would,” “might” or “will” be taken, occur or be achieved. FLS in this news release include, but are not limited to: statements relating to the anticipated sources and uses of funds to complete project financing, GM’s investment in the JV (the “JV Transaction”), the DOE Loan, the strategic investment of $250 million from Orion (the “Orion Investment”), the Warrants, the Put, Call and Exchange Agreement entered into in connection with the issuance of the Warrants, and the Yorkville Debentures, including statements regarding satisfaction of draw down conditions on the DOE Loan, the availability and timing of delayed closings under the Yorkville Debentures, the Company’s ability to satisfy conditions to future delayed closings under the Yorkville Debentures, the anticipated use of proceeds from the Yorkville Debentures and the March 2026 ATM Program, expectations about the extent to which the JV Transaction, the DOE Loan, including any amendments thereto, the Orion Investment, the Warrants, the Yorkville Debentures and cash on hand would fund the development and construction of Thacker Pass on schedule or at all; the estimated incremental funding requirement and anticipated sources of funding therefor, including contributions from the Company to the JV, the potential issuance of additional notes to Orion, sale of common shares pursuant to the March 2026 ATM Program and the use of cash and the GM letter of credit held in reserve accounts maintained in accordance with the DOE Loan and proposed changes to the SCRA requirements; anticipated increases to reserve account requirements under the DOE Loan; the finalization of incremental funding arrangements and any related implications for JV interest holdings and the DOE Loan; project de-risking initiatives and the extent to which work to date has de-risked project execution; the expected operations, financial results and condition of the Company; expectations related to the construction build, job creation and nameplate capacity of Thacker Pass as well as other statements with respect to the Company’s future objectives and strategies to achieve these objectives, including the future prospects of the Company; the estimated cash flow, capitalization and adequacy thereof for the Company; the estimated costs of the development of Thacker Pass, including timing, progress, approach, continuity or change in plans, construction, commissioning, expected milestones, anticipated production and results thereof and expansion plans; cost and expected benefit of the transloading terminal; cost and expected benefit of the limestone quarry; anticipated timing to resolve, and the expected outcome of, any complaints or claims made or that could be made concerning the permitting process in the United States for Thacker Pass; the timely completion of environmental reviews and related consultations, and receipt or issuance of permits and approvals, in the United States for the Company’s development and resultant operations; capital expenditures and programs; estimates, and any change in estimates, of the mineral resources and mineral reserves at Thacker Pass; development of mineral resources and mineral reserves; the realization of mineral resources and mineral reserves estimates, including whether certain mineral resources will ever be developed into mineral reserves, and information and underlying assumptions related thereto; government regulation of mining operations and treatment under governmental and taxation regimes; the future price of commodities, including lithium; the creation of a battery supply chain in the United States to support industries and technologies dependent on lithium batteries, including the electric vehicle and battery energy storage system markets; the timing and amount of future production, currency exchange and interest rates; the Company’s ability to raise additional capital on favorable terms or at all; expected expenditures to be made by the Company; statements relating to revised capital cost estimates, including statements regarding the Capex Estimate; ability to produce high purity battery grade lithium products; settlement of agreements related to the operation and sale of mineral production as well as contracts in respect of operations and inputs required in the course of production; the timing, cost, quantity, capacity and product quality of production at Thacker Pass; successful development of Thacker Pass, including successful results from the Company’s testing facility and third-party tests related thereto; statements with respect to the expected economics of Thacker Pass, including capital costs, operating costs, sustaining capital requirements, after tax net present value and internal rate of return, pricing assumptions, payback period, sensitivity analyses, net cash flows and life of mine; anticipated job creation; the expectation that the National Construction Agreement (Project Labor Agreement) with North America’s Building Trades Unions for construction of Phase 1 of Thacker Pass will minimize construction risk, ensure availability of skilled labor, address the challenges associated with Thacker Pass’s remote location and be effective in prioritizing employment of local and regional skilled craft workers, including members of underrepresented communities; overarching accessibility to a productive workforce; the expected workforce development training program being prepared with Great Basin College; the Company’s commitment to sustainable development, limiting the environmental impact at Thacker Pass and plans for phased reclamation during the life of mine, including use benefits of growth media; ability to achieve capital cost efficiencies; anticipated use of any future proceeds and earnings related to Thacker Pass; anticipated plans regarding the payment or non-payment of dividends, as well as other statements with respect to management’s beliefs, plans, estimates and intentions, and similar statements concerning anticipated future events, results, circumstances, performance or expectations that are not historical facts.
INVESTOR CONTACT
Virginia Morgan
Vice President, Investor Relations and ESG
+1-778-726-4070
ir@lithiumamericas.com
| 6 hours | |
| 6 hours | |
| 9 hours | |
| Nov-10 | |
| Sep-14 | |
| Aug-13 | |
| Aug-13 | |
| Aug-11 | |
| Aug-06 | |
| Jul-16 | |
| Jul-13 | |
| Jun-29 | |
| Jun-25 | |
| Jun-23 | |
| Jun-02 |
Join thousands of traders who make more informed decisions with our premium features. Real-time quotes, advanced visualizations, alerts, and much more.
Learn more about Finviz Elite